WHAT YOU NEED TO KNOW

  • Venture Global moved expected first LNG production from its CP2 complex in Louisiana to July.
  • The first two phases will include 36 liquefaction trains with capacity of about 29 million tonnes/year.
  • Executives expect CP2 to export between 10 and 20 cargos during next year’s third quarter.
  • Venture Global plans an early 2027 investment decision on a third phase adding 10 million tonnes/year of capacity.

Venture Global Inc. has accelerated the schedule for first LNG from its CP2 complex in Louisiana, moving the expected production date to July. The Arlington, Virginia, company had previously targeted the second half of 2027 for the milestone.

Chief executive officer Mike Sabel disclosed the updated timing after Venture Global reported its third quarter results on Nov. 10. He told analysts that construction progress now supports first LNG just 24 months after the company reached its final investment decision on CP2.

The first two phases under construction at the Cameron site, south of Lake Charles, will include 36 liquefaction trains. Together, those phases are designed for capacity of about 29 million tonnes/year.

Lenders have committed about $43 billion to the first two phases of CP2. The scale of that commitment accompanies a project that Venture Global expects to begin producing LNG earlier than the timeline Sabel had previously presented to investors.

Three months before the Nov. 10 conference call, Sabel said he was “being precise” by using the second half of 2027 as the target. At the time, he pointed to the many variables involved in construction.

The latest update reflects the progress workers have made at the Louisiana complex. Sabel also said operations should increase quickly once the facility begins producing LNG, citing Venture Global’s experience with its Plaquemines operation as a guide.

“The best guide is to look at the ramp-up for Plaquemines, which […] produced 234 cargoes in the first 12 months [...] We studied, as we do very carefully, the opportunities to improve on that and we think there are opportunities for improving the ramp-up for CP2 relative to Plaquemines,” Sabel said on a conference call.

“That ramp-up for Plaquemines, we view as a really good baseline opportunity. Given the massive scale of CP2, we think the opportunity there is significant.”

Venture Global executives expect CP2 to export between 10 and 20 cargos during next year’s third quarter. That outlook places the first expected shipments within months of the newly stated July production target.

For comparison, Venture Global’s operations exported 124 cargos during the latest quarter, compared with 100 cargos in the third quarter of 2025. The company’s third quarter cargos contained 467 trillion btu of LNG, up from 372 trillion btu a year earlier.

Expansion work could continue as CP2 moves through its operational ramp. Sabel and his team plan to reach a final investment decision in early 2027 on a third phase that would add 10 million tonnes/year of capacity at the site.

Venture Global reported third quarter net income of $2.55 billion on revenue of $4.76 billion. A $1.4 billion gain on interest rate swaps helped lift the company’s bottom line during the period.

Operating profit rose to about $2.3 billion from $1.32 billion in the prior year quarter. The financial results accompanied higher LNG cargo volumes and the updated CP2 construction timeline presented to analysts.

Shares of Venture Global, trading under the ticker VG, were up about 0.5% to $11.86 in early afternoon trading on Nov. 10. The shares had gained about 4% during the previous six months.

Those gains expanded Venture Global’s market capitalization to nearly $30 billion. Meanwhile, the company is advancing the first two CP2 phases, preparing for July production and considering a third phase that would further increase the Louisiana complex’s LNG capacity.