San Mateo Midstream LLC plans to expand its natural gas gathering and processing infrastructure in New Mexico’s Delaware basin after signing two long term agreements with a producer. The projects include additional processing, pipeline and gas treating capacity.
The agreements comprise a new long term, fixed fee gas gathering and processing contract and an extension of an existing gathering and processing agreement. San Mateo expects both agreements to add long term volumes across its system.
San Mateo is a joint venture between Matador Resources Co., which owns 51%, and Five Point Infrastructure LLC, which owns 49%. Anticipated production growth from Matador also supports the planned infrastructure expansion.
At the center of the program is an expansion of the Marlan natural gas processing complex in Eddy County, New Mexico. San Mateo plans to install a processing train with capacity of 300 MMcfd.
The company also plans to add a new nitrogen rejection unit at the Marlan complex. Together, the installations will expand the site’s ability to process expected gas volumes associated with the new producer agreements and anticipated Matador production.
Beyond the processing complex, San Mateo expects to construct about 20 miles of natural gas pipeline. The pipeline will connect newly dedicated acreage to the company’s gathering and processing infrastructure.
The planned development also includes a field treating facility for CO2 removal. The facility represents another component of the infrastructure required to gather, treat and process gas from the dedicated acreage.
Completion of the Marlan expansion is targeted for yearend 2028. That schedule remains subject to permitting, procurement and construction activities.
The project is expected to increase San Mateo’s anticipated 2026 midstream capital expenditures by about $25 million. The company now estimates its midstream capital budget for the year at $170 million to $190 million.
Under the new gathering and processing agreement, San Mateo will gather and treat natural gas produced from newly dedicated acreage in Lea and Eddy Counties, New Mexico. The gathered volumes will be processed at the Marlan complex.
The agreement includes a large scale acreage dedication in the northern Delaware basin. San Mateo expects the arrangement to contribute additional gas volumes to its gathering and processing network.
Separately, San Mateo amended an existing agreement covering production from Eddy County. Under that extension, gas will continue to be gathered, treated and processed at the Black River gas processing plant in Eddy County for several years beyond the contract’s original term.
The extension builds on a gas gathering and processing agreement that San Mateo announced in October 2018. The company did not identify the producer in the supplied announcement.
Once the Marlan expansion is complete, San Mateo’s total natural gas processing capacity will exceed 1.3 bcfd. That level would be nearly three times the 460 MMcfd of capacity the system had before Matador contributed Pronto Midstream LLC to the venture in December 2024.
Joseph Wm. Foran, Matador founder, chairman and chief executive officer, and founder of San Mateo, said the agreements build on San Mateo’s growth. He also pointed to work connecting the San Mateo and Cardinal systems.
“Following the closing of the previously announced Cardinal Midstream acquisition in the third quarter, we completed the connection of the San Mateo and Cardinal systems in southern Eddy County, New Mexico,” he said.
Foran said another connection is planned for 2027. “In 2027, San Mateo plans to complete the full system connection with a northern pipeline connecting San Mateo’s Lea County gathering infrastructure with the terminus of Cardinal’s gathering infrastructure in Eddy County. This connection is expected to allow gas volumes to flow from the Marlan Plant complex in the north to the Pecos River Plant in the south, providing further flexibility for San Mateo and its customers.”
The northern pipeline is intended to link San Mateo’s Lea County gathering infrastructure with Cardinal’s gathering infrastructure in Eddy County. Foran said the newly signed producer agreements are expected to begin increasing volumes in 2028.