ExxonMobil Greenlights $12.5 Billion Longtail Development Offshore Guyana

Daniel Mercer ·

ExxonMobil Corp. has taken a final investment decision on the Longtail development offshore Guyana, advancing the eighth approved project on the Stabroek block. The company plans to invest an additional $12.5 billion in the development, which is expected to come online in 2030.

The decision followed government and regulatory approvals for the operator’s eighth development on the block. Longtail will expand the sequence of approved Stabroek projects while introducing production focused on gas and condensate resources.

Located in the southeastern portion of the Stabroek block, Longtail will target nonassociated gas and reservoirs rich in condensate. The resource profile differs from the oil production currently flowing from four developments across the block.

Gas produced by the project could eventually be transported to shore through a pipeline. That possibility remains subject to future investment decisions, market demand and the development of supporting infrastructure.

Longtail will use a floating production, storage and offloading vessel. The FPSO will be designed to process 1.2 bcfd of gas and produce as much as 250,000 b/d of condensate.

The planned development is expected to include about 45 subsea production and injection wells. Those wells will support the production and injection requirements associated with the offshore project.

“By developing these gas and condensate resources, we’re unlocking new value for Guyana while delivering advantaged energy to meet growing global demand,” said Dan Ammann, president, ExxonMobil Upstream Company.

Longtail’s expected 2030 startup places it after several other Stabroek projects that are already producing or remain under construction. ExxonMobil currently produces about 900,000 b/d of oil from four developments on the block.

Uaru, the fifth project, is expected to begin production in the fourth quarter of 2026. Its startup is expected to increase total production capacity across the Stabroek block to more than 1 million b/d.

Construction is also continuing on Whiptail and Hammerhead, the sixth and seventh approved projects on the block. Whiptail is scheduled to start production in 2027, while Hammerhead is expected to follow in 2029.

The project schedule therefore extends from Uaru’s expected startup in 2026 through Whiptail in 2027, Hammerhead in 2029 and Longtail in 2030. Each of those timelines was identified for an approved development on the Stabroek block.

Earlier this year, ExxonMobil and its venture partners produced the 1 billionth bbl of oil from Guyana’s Stabroek block. The milestone was reached less than 7 years after first production began from Liza field in December 2019.

The block’s current output of about 900,000 b/d comes from four producing developments. With Uaru expected to lift total capacity above 1 million b/d, work is proceeding on the next projects in the approved development sequence.

Longtail adds a large gas processing and condensate production design to that sequence. Its planned FPSO capacity of 1.2 bcfd and as much as 250,000 b/d of condensate defines the project’s expected production scale.

The potential pipeline connection to shore is not yet presented as a firm component of the development. ExxonMobil said such transportation would depend on additional investment decisions, sufficient market demand and supporting infrastructure.

ExxonMobil Guyana Ltd. operates the Stabroek block with a 45% interest. Hess Guyana Exploration Ltd. holds a 30% interest, while CNOOC Petroleum Guyana Ltd. holds the remaining 25%.

With the final investment decision now taken, Longtail stands as the eighth approved Stabroek development and carries an expected startup date of 2030. The additional planned investment totals $12.5 billion for a project centered on offshore gas and condensate production.